This will only be overwritten with an “actual start date” and I will come back to that later in the post.
If you have ever had the pleasure of working with Microsoft Project you will likely be quite happy with it until you start changing the RESOURCE UNITS percentages (in the TASK INFORMATION pane).
If you make changes you will find that it often miscalculates (or appears to miscalculate) the number of HOURS in WORK.
This will set a scheduling constraint on the task, because MS Project now thinks the task should “start no earlier than” the manually entered date.
There is also a “must start on” option that will completely lock the start date of a task.



You will be able to start a task earlier, but you will be prompted by a message stating: The start of task X is before the project starts.